Alberta Court of Appeal Decision Raises Limitation Risks for Construction Claims
November 26, 2026
Chandos Construction Ltd v Associated Engineering Alberta Ltd, 2026 ABCA 376
The Alberta Court of Appeal’s decision in Chandos Construction Ltd v Associated Engineering Alberta Ltd, 2026 ABCA 376 is an important reminder for contractors, owners and consultants that limitation periods for construction claims may begin running well before substantial performance of the project.
Chandos was the general contractor for a water treatment plant project, with Associated Engineering Alberta Ltd. acting as design consultant and contract administrator. During construction, Chandos issued a series of notices identifying delays, additional work and resulting cost impacts that it attributed to the owner or consultant. Although substantial performance was not achieved until September 26, 2018, the Court concluded that, for the claims at issue, Chandos had the knowledge required under Alberta’s Limitations Act before July 11, 2018. Most of the Chandos delay and additional-work claims were therefore summarily dismissed as limitation-barred.
Importantly, the Court did not require Chandos to have certainty of the quantum of its losses or whether they would ultimately be compensated by the Owner or Consultant before the limitation period could run. The contemporaneous notices, together with the pleadings and evidence, demonstrated that Chandos knew it was experiencing significant, rather than merely trivial, cost and delay impacts and attributed those impacts to the defendants.
For the construction industry, the timing is particularly significant: contractors cannot assume that substantial performance will start the two-year limitation clock. Depending on the circumstances, the limitation period may already be running while construction continues and before the cumulative impact of delay or additional work can be fully quantified. Similarly, waiting for a claim to be formally submitted or rejected may not postpone the limitation period where the contractor already has sufficient knowledge of the alleged wrongful conduct and some resulting cost impact.
The decision also highlights a tension inherent in construction claims administration. Contractors are typically required to give prompt notice of delays, extras and other impacts to preserve contractual entitlements. Those same notices, together with project records and other evidence, can also demonstrate when the contractor knew enough about its loss and its cause to trigger the statutory limitation analysis. This does not mean that every contractual notice starts the limitation clock, but a notice identifying responsibility and a material cost or delay impact should prompt an immediate limitations assessment.
Ongoing negotiations also do not, by themselves, suspend the limitation period. While the Court recognized that an established contractual dispute-resolution process may affect when proceedings are warranted in an appropriate case, a party seeking to rely on that process must actually invoke and comply with it to impact the limitations period.
Justice Feth, dissenting, rejected the majority’s effective treatment of knowledge of a non-trivial loss as sufficient to establish that an injury “warrants bringing a proceeding” under s. 3(1)(a)(iii) of the Limitations Act. In his view, a significant loss attributable to another party is necessary, but not necessarily sufficient, to trigger the limitation period; the inquiry remains fact-specific and asks whether a reasonable person in the claimant’s circumstances had sufficient reason to commence litigation. In the construction context, Feth J.A. cautioned that treating non-trivial cost or delay as sufficient to start the limitation period running does not give full effect to the policy considerations that underpin the limitations analysis. The majority decision could encourage premature litigation during ongoing projects and undermine the statutory objective of avoiding unnecessary “placeholder” actions.
The practical takeaway from the case is that contractual claims administration and statutory limitation periods need to be managed on parallel tracks. Contractors should assess potential limitation dates when significant claims arise rather than automatically diarizing two years from substantial performance or final claim determination. Owners and consultants should likewise preserve early notices, RFIs, change requests, schedules and cost records that may establish when a claim became discoverable. Where the parties want to continue working toward a commercial resolution without commencing proceedings, an express limitation extension or standstill agreement should be considered.
For Alberta construction participants, the central message is straightforward: by the time a project reaches substantial performance, the limitation period for an unresolved construction claim may already have been running for some time.